Subcontractor agreement: what it should cover
A subcontractor agreement should settle, in writing and before work starts, the parties, the scope, the price and billing, payment and retainage (the share of each payment an owner holds back until the work is done) terms, lien waivers, change orders, schedule, insurance, safety, warranty, termination, disputes and which parts of the prime contract bind the sub. Our free checklist lists all fourteen topics.
Why we give a checklist and not a sample
Searches for a sample subcontractor agreement are common, and a web sample is the wrong tool: it was written for another state and another risk. What helps is knowing what the agreement has to settle, so that you can check any form, your own or a published standard one, against it. Industry bodies such as the AIA and ConsensusDocs sell standard subcontract forms, and your attorney can draft or adapt one for your work.
The fourteen topics
Parties, project and scope
Use the exact legal names and license numbers of both parties, the project address, the owner, and the prime contract the subcontract falls under. A wrong entity name is a common reason a payment claim or lien notice is rejected. Scope should list what is included, what is excluded, and the drawings, specifications and addenda it is based on, with their dates. Most subcontract disputes start with an item both sides assumed the other would cover.
Price, billing and payment
State the pricing type (lump sum, unit price or time and materials), attach the schedule of values (the contract price split into billable lines) used for progress billing, and set the billing date, the due date and the retainage rate with its release trigger. Check how your state treats pay-when-paid and pay-if-paid terms, because the rules differ and some terms may be restricted.
Lien waivers
Say which waiver type is due with each application, who prepares it, and that the state's statutory form is used where a statute requires one. See lien waivers by state for the statutes we read. Agree, too, that an unconditional waiver is given only after payment has cleared.
Change orders and schedule
Say how a change is priced, who may approve it and that work on a change does not begin until it is signed. See change orders. Set the start date, milestones, how delay is notified and any liquidated damages passed down from the prime contract. A sub inherits the prime contract's time pressure.
Insurance, safety and site rules
List the required coverages and limits, the certificate holder and additional insured wording, and any bond. Attach the safety plan and note site access, badge and cleanup rules, which are often in a separate document that nobody attaches.
Warranty, termination and disputes
State the warranty period and the call-back process, the punch list timeline, the notice and cure steps before termination and what happens to materials and unpaid work, and the dispute path (notice, mediation or arbitration, venue and fees). Keep it consistent with the prime contract.
Flow-down and attachments
Say which clauses of the prime contract bind the sub, and attach or clearly reference them. List every attachment so the signed package is complete: scope, schedule of values, insurance requirements, drawings and the safety plan.
Questions to ask at signing
- Does the sub's scope match the line items it will bill against?
- Does the sub know the payment terms, including when it is paid relative to the owner?
- Does it have the lien waiver (a signed paper that gives up the right to claim against a property for unpaid work) forms and the due dates?
- Who at the sub is allowed to sign change orders?
- When does each insurance certificate expire?
Free: subcontractor agreement checklist
Fourteen topics with what to settle, why it comes up, and columns to mark what is agreed and where it sits in your contract.
Download the subcontractor agreement checklist (xlsx) (no email needed).
Informational only. This is not a contract, not legal advice and not a substitute for a construction attorney in your state.
Questions people ask
Where can I get a sample subcontractor agreement?
Industry bodies publish standard forms, for example the AIA (which lists trade agreements) and ConsensusDocs (which lists a subcontracting package of 28 contracts), and many attorneys keep their own. We do not post a sample agreement, because a contract copied from a website is the wrong tool for a document that allocates risk. Our checklist lists what the agreement should settle, to take to your attorney.
What does pay-when-paid mean in a subcontract?
A term making the general contractor's payment to the sub depend on the owner's payment to the general contractor, in one of its forms. Whether it is enforceable, and in which form, depends on your state, and some states restrict it. Read the clause and ask your attorney before you accept or rely on one.
What is a flow-down clause?
A clause that makes the subcontractor bound by selected terms of the prime contract between the owner and the general contractor. A sub cannot comply with terms it has not seen, so the prime contract, or the relevant parts of it, should be attached or clearly referenced.
Does the checklist replace a contract?
No. It is a list of topics to settle in writing before the sub starts. The contract itself should be drafted or reviewed by a construction attorney in your state.
How should a general contractor track subcontractor insurance?
By expiry date. Record each certificate's expiry in one place and ask for the renewal before it lapses, because a certificate that expired mid-job is a gap in your own protection. This is one of the simplest tasks to automate.
Sources and date checked
Every statute, vendor and price statement on this page was read on the page linked below on the date shown. Where a vendor page did not say something, this page says so instead of guessing. The links go to the original pages, not to summaries.
- AIA Contract Documents (lists A-Series trade agreements), checked 2026-11-23
- ConsensusDocs (lists a subcontracting package of 28 contracts), checked 2026-11-23