Home / Change orders in construction: how they work
Change orders
Change orders in construction: how they work
A change order (a signed change to the contract's scope, price or time) is a written, signed change to a construction contract that adjusts the scope of work, the price, the time, or all three. Its job is to turn extra or changed work into agreed money before the work is done, so that it can be billed like the rest of the contract.
Why change orders exist
No set of drawings survives contact with a job site unchanged. The owner asks for a different finish, a field condition turns out differently from the plans, an inspector asks for something extra, or a design team issues a revision. Each of those changes the work you agreed to price. The change order is the document that records the new agreement: what changed, what it costs or saves, and how many days it adds or removes. Without it, the extra work is a dispute waiting for the final payment.
What a change order contains
- Identification: the project, the contract, the change order number and the date.
- Description of the change: specific enough that a stranger could tell what was added or removed, with the reference that triggered it (a drawing revision, an RFI, which stands for request for information, an email or a site instruction).
- Cost: an amount to add or deduct, with a breakdown of labor, materials, equipment, subcontractors and markup.
- Time: days added or removed, and the new completion date if it moves.
- Contract sum: the sum before the change, the change, and the sum after.
- Signatures: the parties with authority under the contract, and dates.
Steps from request to signature
- Notice. Check your contract's notice clause the moment something looks like a change. Many contracts set a deadline for notifying the other side, and missing it can cost you the claim.
- Document the trigger. Keep the email, drawing revision, RFI answer or photograph that started it. Date it.
- Price it. Quantities times your own unit costs, plus subcontractor quotes, plus markup as your contract allows. If an item is deducted, price the deduction too.
- Address time. Decide whether the change moves the schedule and say so in the document.
- Submit and get it signed. By the person the contract names, before the work starts where you can.
- Log it. Add it to the change order log and update the contract sum, so that the next pay application (the monthly request for payment) includes it.
- Bill it. Add a line to the schedule of values (the contract price split into billable lines) for the approved amount, or bill against the existing lines your contract specifies.
Pricing methods, in plain words
Contracts tend to name how change work is priced. The common ones are a lump sum for the change, unit prices that were agreed in advance (so much per cubic yard or per linear foot), and time and materials with a not-to-exceed cap. Each needs different backup: a lump sum needs a breakdown, unit prices need quantities, and time and materials needs daily records of hours and materials, which is why a good daily report pays off at change order time.
Illustration (hypothetical numbers): the owner asks for six extra recessed lights. The electrician quotes $1,320, and your contract allows 10% markup on subcontractor work. The change order adds $1,452 and, because the fixtures have a four-week lead time, adds 5 days. The same change priced without addressing time would have left you owing the original completion date.
Where change orders go wrong
- Work before signature. Extra work with no signed change order is the classic unpaid item.
- Time left out. The price is agreed, the schedule is not, and a delay claim is lost.
- Pricing from memory. The change order amount does not match what the work cost and nobody can show why.
- Chain breaks. The owner signs a change order with the general contractor, but the subcontractor who does the work never gets its own change order, or the reverse.
- Not billed. An approved change sits in an email and never reaches the pay application. The log exists to prevent this.
- Waived by a lien waiver (a signed paper that gives up the right to claim against a property for unpaid work). In California, the statutory waiver text releases rights based on work under a change order fully executed before signing unless it is listed as an exception. See California lien waiver forms.
Forms you will meet
The American Institute of Architects (AIA) lists change orders among its standard documents for the construction phase. We do not reproduce them. Our change order form page explains the fields and provides a generic template of our own for work that does not require the AIA form.
Free: change order log
Original contract sum, approved and pending changes, days added, and a signed-by-owner column, with the current contract sum worked out for you.
Download the change order log (xlsx) (no email needed).
Informational only. This is general information about how change orders work, not legal advice. Notice periods, authority to approve and pricing rules come from your contract and your state's law.
Questions people ask
Do I have to stop work until a change order is signed?
Your contract decides. Many contracts say extra work is not payable without a written, signed change, which is a reason to wait. Some let the owner direct work before the price is agreed and settle the price after. Read the changes clause of your own contract and ask your attorney before you proceed on a verbal go-ahead.
What is the difference between a change order and a change order request?
A request (sometimes called a proposal request or a potential change order) asks for a price and time impact for a possible change. A change order is the signed agreement that changes the contract. The request comes first and may never become a change order.
Can a change order add time as well as money?
Yes. A change order can add or deduct cost, add or deduct days, or do both. If you price a change without addressing time, you may have agreed to finish the changed scope by the original date.
How should a subcontractor handle a change order the owner has not approved yet?
Submit the price to the contractor in writing, keep the written request or instruction that triggered it, and check the subcontract for notice deadlines. Our change order log records the status and the signature date for exactly this reason.
What is a unilateral change order?
A change the owner issues without the contractor's agreement on price or time, where the contract allows it. Whether your contract allows that, and what you must do if you disagree (usually notice within a stated number of days), is a contract question to settle with your attorney.