Change order log: a free spreadsheet and how to use it
A change order (a signed change to the contract's scope, price or time) log is a running list of every change on a project, with its cost, days, status and signature date, and the current contract sum calculated from the approved ones. Ours is a free Excel file that totals approved and pending changes for you.
What the log is for
A change order log answers three questions at any moment. What is the contract worth now? What has been approved but not billed? What have we asked for and not been given? On a job with a dozen changes, nobody carries those answers in their head, and the only copy of the truth is a scatter of emails. The log puts them on one sheet that anyone in the office can read.
The columns and why each is there
- CO number and date requested. The date you raised it is the date that matters if notice deadlines apply.
- Description and requested by. Who asked for the change and what it is.
- Reference. The RFI, email or drawing that triggered the request.
- Cost impact. Positive for an addition, negative for a deduction. The sheet formats negatives in red.
- Days added. Time is part of the change.
- Status. Pending, Approved, Rejected or Withdrawn, from a drop-down. Only Approved changes count toward the current contract sum.
- Date approved and signed by owner. The signature column is the one that prevents unpaid extras.
The four numbers at the top
| Original contract sum | You enter this once. |
|---|---|
| Approved change orders | Added up from every row whose status is Approved. |
| Current contract sum | Original plus approved. This is the number your next pay application starts from. |
| Pending, not yet approved | Added up from every row whose status is Pending. Your exposure on work you may already have started. |
We tested the calculations with sample numbers in a spreadsheet program on 2026-11-23: a $1,000 original sum with one $100 approved and one $50 pending change gave a $1,100 current sum and $50 pending.
Reconciling the log to billing
- Before each pay application (the monthly request for payment), total the approved changes in the log.
- Compare that total to the net change orders on the application.
- For any difference, find the change order by number. Either an approved change was not added to the billing, or one that is still pending was billed.
- Add each approved change as a line in your schedule of values, or bill it the way your contract says.
Habits that make the log worth keeping
- Log a change when it is first raised, not when it is approved.
- Never reuse a number, and never delete a row.
- Put the date you sent each pending change in the notes column, and chase at a fixed interval.
- Share the file read-only with the project manager and the owner's representative, so the contract sum is never in dispute.
Free: change order log
Room for 200 changes, a status drop-down, and the contract sum and pending totals calculated for you.
Download the change order log (xlsx) (no email needed).
Questions people ask
Should rejected change orders stay in the log?
Yes. Keep them with the status Rejected or Withdrawn and a note on why. The number sequence should never have gaps, and a rejected request often returns in a different form later.
How often should the change order log be reconciled to the pay application?
Every billing period. Before you submit a pay application, the net approved changes in the log should equal the net change orders on the application. A difference means an approved change was missed or an unapproved one was billed.
What does the Pending total mean?
It is money you have asked for and not yet been given authority to bill. It is also your exposure if you have started the work. A large pending number is a reason to chase signatures, not to wait.
Can the log hold changes for several projects?
Use one file per project. A shared log across projects hides which contract each change belongs to and makes the contract sum meaningless.