Home / AIA billing explained: pay applications and progress payments
Pay applications
AIA billing explained: pay applications and progress payments
AIA billing is progress billing on the American Institute of Architects' payment application forms: a cover page (the G702) that summarises the contract and what is due, and a continuation sheet (the G703) that breaks the work down by schedule-of-values line. The contractor applies, the architect certifies and the owner pays.
The two documents
On a project that uses AIA documents, each monthly payment request has two parts. The first is the application and certificate for payment, the G702. It is the contractor's request and the architect's certification on one page. The second is the continuation sheet, the G703, which lists each line of the schedule of values with how much has been completed. The G703 totals roll up to the G702.
We do not reproduce AIA documents. AIA sells them, and we do not copy them. What follows explains what the documents do so you can understand any pay application (the monthly request for payment), AIA or not. Our free worksheet carries the same information in a layout of our own. Your contract names the edition it requires.
What the cover page summarises
In plain words, a cover page of this kind tells the owner five things in sequence: the original contract sum; the net of all approved change orders; the current contract sum, which is the first two added; the total completed and stored to date; and from that total, the retainage (the share of each payment an owner holds back until the work is done) held. Subtract the retainage to get the amount earned, subtract what earlier applications already paid, and you have the current payment due, with the balance to finish below it. Every line on the cover page is a total from somewhere else: the contract, the change order (a signed change to the contract's scope, price or time) log, and the continuation sheet.
What the continuation sheet does
The continuation sheet is the schedule of values (the contract price split into billable lines) with columns for the work billed in earlier periods, this period, materials stored but not installed, the total of those, the percent complete, the balance to finish and the retainage. If you can read one pay application, you can read all of them, because the arithmetic does not change. The example on our schedule of values page shows it with two lines.
The monthly cycle
- Cut-off. The contract sets a billing period and a cut-off date. Work after the cut-off belongs to the next application.
- Measure progress. The project manager and superintendent walk the work and set percent complete on each line. This is the judgment step.
- Add changes and stored materials. Approved change orders become lines or adjustments. Stored materials need whatever backup your contract requires.
- Build the application. The sheet totals; check that the lines still equal the current contract sum.
- Collect the backup. Lien waivers from each subcontractor and supplier for the period, insurance certificates, and any other items the contract lists. See conditional and unconditional lien waivers.
- Submit. To the architect or owner's representative, by the date in the contract.
- Review and certification. The reviewer may certify the full amount, a lower amount, or send it back with comments.
- Payment. The owner pays within the contract's time. The cleared payment is what lets you sign unconditional waivers.
Retainage in the application
Retainage is the percentage of each payment the owner holds back until the work is done. The cover page and the continuation sheet both show it, and most contracts set the rate, any step-down and the release trigger. A common source of error is applying one rate to everything when the contract treats stored materials or subcontractor work differently. Our worksheet applies one rate you enter at the top; change the formula if your contract differs.
Where applications get returned
- The lines do not add up to the current contract sum, usually because a change order was missed.
- A line is billed above its scheduled value.
- Previous payments on the application do not match what the owner actually paid.
- A lien waiver is missing, wrong, or for the wrong period.
- Stored materials are billed without the required backup.
Each of these can be checked automatically before submission, which is why this is the first workflow we would look at with a general contractor.
Free: progress billing worksheet (our own layout)
Schedule of values lines, percent complete, retainage and a billing summary. Not an AIA form; use it to check the math or when your contract does not require AIA forms.
Download the progress billing worksheet (xlsx) (no email needed).
Questions people ask
What is the difference between a G702 and a G703?
As AIA describes them, the G702 is the cover application: the contractor's request for payment and the architect's certification. The G703 is the continuation sheet that lists the schedule of values line by line, with what has been completed and stored on each. The totals on the G703 feed the G702.
Do I need to buy the AIA forms to bill progress?
Only if your contract requires AIA forms. AIA sells its contract documents, including this one. If your contract does not name them, you can use your own layout that carries the same information, such as our free worksheet. Check your contract first.
Who certifies the pay application?
On projects with an architect, the architect reviews the application and certifies the amount due, then the owner pays. On projects without one, the owner or owner's representative reviews it. The contract names the reviewer and the time allowed.
What goes with the pay application besides the forms?
Contracts typically add lien waivers from the contractor and subcontractors, insurance certificates, and backup for stored materials and change orders. The exact list is in your contract's payment article.
Is AIA billing the same as progress billing?
Progress billing is the general method of billing for work completed each period. AIA billing means progress billing on the AIA application forms. People say it for either, which is why searches for AIA billing include contractors who only want to learn the method.
Sources and date checked
Every statute, vendor and price statement on this page was read on the page linked below on the date shown. Where a vendor page did not say something, this page says so instead of guessing. The links go to the original pages, not to summaries.
- AIA Contract Documents (publisher of the G702 and G703), checked 2026-11-23
- AIA Contract Documents help: Summary of the G702-1992 (read for this page), checked 2026-11-23