Home / Schedule of values in construction: what it is and how to build one
Schedule of values
Schedule of values in construction: what it is and how to build one
A schedule of values (the contract price split into billable lines) is a breakdown of the total contract price into line items, each with a dollar value, that the contractor uses to bill progress on each pay application (the monthly request for payment). Each line shows how much is complete, so the owner pays for what has been built and holds back the rest.
What it does on a job
The contract gives a single price. The owner is not going to pay a single payment for the whole job at the end, so the contractor and owner need a way to agree on what has been earned each month. The schedule of values is that agreement: it divides the price into pieces (site work, concrete, framing, mechanical, electrical, closeout), and each month the contractor reports how much of each piece is done. The sum of the pieces times their percent complete is what has been earned to date. It is the foundation of progress billing, and it is submitted and approved before the first pay application.
Building one from an estimate
- Start from the final estimate. The contract price is the total, including overhead and profit. The schedule has to add up to exactly that number.
- Group the lines the way the owner will review them. Often by trade or by specification division. Keep your own cost codes next to each line so you can match job cost later.
- Spread overhead and profit. Add them proportionally across the lines instead of showing them as a separate large line, unless the contract says otherwise. A large overhead line at the top is front-loading.
- Add general conditions as lines you can measure. Mobilization, supervision, temporary facilities and cleanup, each with a clear way to judge progress.
- Add allowances and alternates as separate lines. This lets you bill them at their own pace.
- Check the total. The worksheet below flags a difference between the lines and the contract sum.
- Submit it for approval before the first application. Changing it later is harder than getting it right the first time.
The columns on a billing sheet
Whatever the layout, the same quantities appear on every progress billing. Our free worksheet carries them in our own arrangement:
- Scheduled value: the line's share of the contract price.
- Billed in earlier periods: what previous applications already claimed.
- Billed this period: work completed since the last application.
- Materials stored: materials bought and delivered or stored but not yet installed, if your contract allows billing for them.
- Total completed and stored: the sum of the three above.
- Percent complete: total completed and stored divided by scheduled value.
- Balance to finish: scheduled value less total completed and stored.
- Retainage (the share of each payment an owner holds back until the work is done): the amount held back, as a percentage of the total completed and stored.
A small worked example (hypothetical)
Contract sum $1,000, retainage 10%. Line one has a scheduled value of $600, with $100 billed earlier, $200 billed this period and $50 of stored material. Total completed and stored is $350, which is 58.3% complete, with $250 left to finish and $35 held as retainage. Line two has a $400 scheduled value with $100 billed this period: $100 complete, 25%, $300 left, $10 retainage. Across both lines, $450 is complete and stored, $550 remains, and $45 is held. We checked these figures by running them through the free worksheet on 2026-11-23.
Mistakes that cause trouble
- Front-loading. It invites a revision, and a reviewer who finds it will question the whole application.
- Lines too big to judge. "Building shell" at $400,000 cannot be approved at 40% without argument.
- Stored materials without documentation. Contracts that allow billing for stored materials normally ask for invoices, insurance and a stated storage location.
- Forgetting changes. Approved change orders have to reach the schedule, or the total stops matching the contract sum.
- Mismatched cost codes. If the schedule and the estimate use different codes, comparing billing to cost becomes manual.
The AIA payment application has a continuation sheet that lists the contract by line, as described on our AIA billing page. Our sheet is our own layout and does not copy any AIA form; if your contract requires AIA forms, use those forms and use ours to check the arithmetic.
Free: schedule of values and progress billing worksheet
50 lines, percent complete and retainage calculated, a check that the lines match the contract sum, and a billing summary sheet.
Download the schedule of values and billing worksheet (xlsx) (no email needed).
Questions people ask
What is front-loading a schedule of values?
Assigning more value to early line items (mobilization, general conditions, early trades) than the work is worth, so that early pay applications are larger. Owners and architects watch for it, because it shifts risk to the owner. A schedule of values built from real cost plus a fair share of overhead and profit holds up to review; one weighted toward the first months invites a revision.
Is a schedule of values the same as a bid breakdown?
They are related. A bid breakdown shows how the price was built; the schedule of values divides the final contract price into billable lines. Many contractors start from the estimate and then regroup the lines into the sections the owner wants to see on the pay application.
How many lines should a schedule of values have?
Enough that percent complete is easy to judge on each line, and few enough that the pay application can be reviewed. A line that covers three months of work is too coarse to bill fairly; a line for every box of screws is too fine. Your contract or the architect may set a minimum level of detail.
Does the schedule of values change when a change order is approved?
Usually yes. An approved change order adds, or deducts from, the contract sum, and billing follows by adding lines or adjusting existing ones in the way your contract specifies. Keep the original lines and add the changes below them, so you can see the original contract and the changes separately.
Does retainage come out of each line or the total?
The worksheet takes retainage as a percentage of the total completed and stored on each line and adds it up, which equals a percentage of the total. Your contract may set a different rate for materials or may reduce retainage after a milestone, so check it.