Home / Construction estimate template: format and how to use it

Estimate template

Construction estimate template: format and how to use it

A construction estimate lists each piece of work with a cost code, a quantity, a unit cost and a markup, adds contingency and permits, and ends in a total. Our free Excel template does the multiplication and totals for you and leaves the cream cells for your own numbers.

The format in one picture

Every estimate, from a bathroom remodel to a warehouse, is built from the same row: what the work is, how much of it there is, and what a unit costs. The rows are grouped so the reader can see where the money goes. The template has eight columns:

Cost codeA short label that groups the line with its trade or phase. Use the same scheme on every job.
DescriptionWhat the work is, specific enough that a stranger could price it.
Quantity and unitHow much, and in what unit: square feet, linear feet, each, lump sum.
Unit costYour cost per unit from vendor quotes and past jobs.
Line costQuantity times unit cost. Calculated.
Markup percentYour overhead and profit for this line.
Line priceLine cost times one plus the markup. Calculated.

Below the lines the sheet adds contingency as a percentage of the subtotal, permits and fees, and a total. Nothing in the template is a price list; every number in the cream cells is yours.

Markup and margin: do the arithmetic once

This is the most common estimating error, and it is plain arithmetic. Say a line costs $10,000 and you want to earn 20 cents on every dollar of price. A markup of 20% gives a price of $12,000, on which your profit of $2,000 is 16.7% of price, not 20%. To earn a 20% margin you need a price of $12,500, which is a 25% markup. The template uses markup percent because that is how most estimates are built; if your target is a margin, convert it: markup equals margin divided by one minus margin.

Building an estimate that survives review

  1. Read the drawings and specs once before you price. Note exclusions and unusual requirements as you go.
  2. Take off quantities by trade. Keep the takeoff next to the estimate so any quantity can be traced.
  3. Price from sources you can name. A vendor quote, a past invoice, a labor rate with its burden. Note the source and the date in the description.
  4. Add labor productivity where it matters. Hours per unit multiplied by a loaded hourly rate, then entered as a unit cost.
  5. Add general conditions as lines. Supervision, temporary facilities, cleanup, insurance and bonds belong in the estimate, not just in overhead.
  6. Apply markup consistently. One policy, not a number chosen by feel on each line.
  7. Add contingency and permits. Show them separately.
  8. Have someone else read it. A second pair of eyes finds a missing trade faster than a second pass by the same person.

What to carry forward to the next stage

Estimates are used twice. The first use is to produce a price. The second is the comparison later: how did the job cost against what you estimated? That works only if the cost codes in the estimate match the codes you post actual costs against. The estimate also becomes the base of your schedule of values for billing and the starting list of exclusions that may later become change orders. Turn the finished estimate into a client document with the bid and proposal template.

When a spreadsheet stops being enough

A spreadsheet is a good estimating tool for a small shop. It runs out when several people estimate in parallel, when you want a catalogue of material prices that updates itself, or when takeoff and estimate need to stay in sync. Then you are choosing between estimating tools, each with its own import and export options. See construction estimating software compared and takeoff software for what each vendor lists on its own pages.

Free: construction estimate template

100 lines, cost codes, line markup, contingency and permits, with totals worked out.

Download the estimate template (xlsx) (no email needed).

The pack is every spreadsheet and printable form on this site in one zip. We send one email to confirm your address, then a link to the pack. Unsubscribe any time. Or download the pack now.

Questions people ask

What is the difference between markup and margin?

Markup is added to cost; margin is a share of the price. A 25% markup on $100 of cost gives a $125 price, and the margin on that price is 20%, because $25 is 20% of $125. Mixing the two is a common reason a job earns less than the estimate said it would.

What is a cost code?

A short label that groups costs by type of work, such as a number for framing labor or for concrete materials. Using the same codes on estimates, purchase orders, timesheets and billing lets you compare what you estimated with what you spent.

How do I price an estimate that has a lot of quantity takeoff?

Take the quantities off the plans (by hand or with a takeoff tool), enter them in the quantity column with their unit, and apply unit costs from your vendors and past jobs. Our guide to takeoff software lists the tools and what each publishes.

Should contingency be a line item or built into unit costs?

Show it as its own line if the client will see the estimate, so they understand what it is and how it is used. Bury it in unit costs and a reviewer who spots one inflated unit cost will doubt the rest. Our template carries contingency as a percentage line at the bottom.