Lien waiver rules by state: the statutes we read
In three of the six states on this page (Arizona, California, Nevada) a waiver counts only if it follows the statutory form. Florida has two statutory forms but enforces a different waiver by its own terms. Michigan and Missouri set timing rules in the sections we read, with no form text.
The table
Each row is one statute, read on 2026-11-23 from the source linked at the bottom of this page.
| State and statute | What we read | Form text? |
|---|---|---|
| Arizona A.R.S. 33-1008 | A claimant's waiver is unenforceable unless it follows substantially one of the statutory forms and is signed. A conditional release needs evidence of payment, such as the claimant's endorsement on a paid check or a written acknowledgment. | Yes: four forms |
| California Civ. Code 8132, 8134, 8136, 8138 | The state contractors board says a waiver and release must follow, substantially, one of the four forms in those sections to be effective, and that a conditional release is binding only if there is evidence of payment. | Yes: four forms |
| Florida Fla. Stat. 713.20 | A lien right may not be waived in advance. A waiver may cover only labor, services or materials already furnished. No one may demand a form different from the statutory forms; a waiver not substantially similar is enforced by its own terms. | Yes: two forms (progress, final) |
| Michigan MCL 570.1115 | An advance waiver in a contract is invalid except to the extent payment was made. A claimant paid in full provides a full unconditional waiver. Conditional waivers take effect on payment. | No form text in this section |
| Missouri RSMo 429.005 | A waiver made in anticipation of and in consideration for the award of a contract is against public policy and unenforceable. The section does not prohibit requiring lien waivers as a condition for payment. | No form text in this section |
| Nevada NRS 108.2457 | A contract term that waives lien rights is void. A waiver is enforceable only in the statutory form, and a conditional one only on receipt of payment. A two-party joint check counts as payment for the least of three amounts. | Yes: progress and final forms |
What the pattern tells you
Read across the rows and three things repeat. First, these states treat a lien waiver (a signed paper that gives up the right to claim against a property for unpaid work) as valid only to the extent the claimant was actually paid: Florida, Michigan, Arizona and Nevada all say so in some form. Second, the wording is often fixed by the statute, and the penalty for straying is that the waiver does not count. Third, the unconditional forms carry loud warnings (Arizona and California both state that the document is enforceable against you if you sign it, even if you have not been paid), because signing one before the money clears is the costliest mistake in the paperwork.
What this page does not cover
- Any other state. Nothing on this page implies another state has, or does not have, a statutory form.
- The lien filing, notice and deadline sections for these states. A waiver is one piece of lien law.
- Case law on how courts apply the word "substantially."
- Notarization requirements. The sections and forms we read do not mention them.
Per-state detail pages
For Arizona and California we have walked through the statutory forms one by one: Arizona lien waiver forms and California lien waiver forms. The tracker below carries the same six statutes on a sheet, so each waiver you log can cite the statute it was prepared under.
Free: lien waiver tracker with the six statutes on a sheet
Log the type, form and statute for each waiver. The Check column flags unconditional waivers with no cleared payment.
Download the lien waiver tracker (xlsx) (no email needed).
Informational only. This is a summary of public statutes by a software company, not legal advice. A short summary leaves out exceptions. Use the official statute and a construction attorney for the form you sign.
Questions people ask
Which states require a statutory lien waiver form?
Of the six states on this page (Arizona, California, Florida, Michigan, Missouri and Nevada), Arizona, California and Nevada make a waiver effective or enforceable only if it follows the statutory form. Florida sets two statutory forms but enforces a non-conforming waiver by its own terms. The Michigan and Missouri sections we read set timing rules and contain no form text. We make no claim about other states.
Why does this page list only six states?
Because we list only what we read on an official page: a legislature's own statute site or, for California, the state contractors board's page of the statutory forms. A longer list copied from a secondary source would carry errors we could not check. We add a state only after reading it there and recording the date.
How current is this page?
Every row was read on 2026-11-23. Statutes are amended, so the date matters; the source links go to the official pages.
Can the form change by project type?
Some states apply waiver rules to certain kinds of projects, such as private or public works, and have separate rules for each. We summarise only the sections named in the table. Read the whole chapter for your project type.
Sources and date checked
Every statute, vendor and price statement on this page was read on the page linked below on the date shown. Where a vendor page did not say something, this page says so instead of guessing. The links go to the original pages, not to summaries.
- Arizona A.R.S. 33-1008 (Arizona Legislature), checked 2026-11-23
- California Contractors State License Board: waiver and release forms (Civil Code 8132, 8134, 8136, 8138), checked 2026-11-23
- Florida Statutes 713.20 (Florida Legislature), checked 2026-11-23
- Michigan MCL 570.1115 (Michigan Legislature), checked 2026-11-23
- Missouri RSMo 429.005 (Missouri Revisor of Statutes), checked 2026-11-23
- Nevada NRS chapter 108 (Nevada Legislature), checked 2026-11-23