Arizona lien waiver forms (A.R.S. 33-1008)
Arizona A.R.S. 33-1008 says a claimant's waiver and release is unenforceable unless it follows substantially one of four statutory forms and is signed, and a conditional release works only if there is evidence of payment. The forms cover conditional and unconditional releases for progress and final payments.
How the section is organised
Section 33-1008 is one section with lettered subsections. Subsection A is the rule that stops a contract from waiving other people's liens and sets what a valid waiver requires. B says oral or written statements do not count unless they follow the statutory waiver or the claimant has been paid in full. C protects accord and satisfaction and settlements that reference the lien. D sets the four forms. We read the whole section on the official Arizona legislature site on 2026-11-23.
Subsection A: what makes a waiver effective
An owner or contractor may not waive or impair other persons' claims or liens by contract, with or without notice, except with their written consent or as the statute prescribes, and any contract term to that effect is void. Written consent from a claimant is unenforceable unless the claimant executes and delivers a waiver and release. That waiver and release releases the property for the benefit of the owner, the construction lender, the contractor and the surety on a payment bond only if it follows substantially one of the statutory forms and is signed by the claimant or authorised agent, and, for a conditional release, only if there is evidence of payment. Evidence of payment may be the claimant's endorsement on a single or joint payee check that the drawee bank has paid, or a written acknowledgment of payment from the claimant.
Subsection D: the four forms
| Form | Circumstances | Key text in the form |
|---|---|---|
| Conditional waiver and release on progress payment | The claimant is not in fact paid in exchange for the waiver, or a single or joint payee check is given. | On receipt of a check, in a stated amount, from a named maker, and when it has been endorsed and paid by the bank on which it is drawn, the document releases the claimant's rights to the stated extent. |
| Unconditional waiver and release on progress payment | The claimant asserts in the waiver that it has been paid the progress payment. | The claimant has been paid and received a progress payment in a stated sum and releases its rights to the stated extent. |
| Conditional waiver and release on final payment | Final payment: not paid in exchange, or a check is given. | Effective when the named check is endorsed and paid; covers the final payment for all labor, services, equipment or materials, except for disputed claims in a stated amount. |
| Unconditional waiver and release on final payment | The claimant asserts it has been paid in full. | States the claimant has been paid in full and releases its rights, except for disputed claims for extra work in a stated amount. |
The progress forms release rights "to the following extent": the release covers a progress payment for work furnished through a stated date "only and does not cover any retention, pending modifications and changes or items furnished after that date." They also carry a warranty, in the signer's name, that it has paid or will use the money received to promptly pay in full its laborers, subcontractors, materialmen and suppliers for work provided through the date of the waiver. Each unconditional form must carry a notice in type at least as large as the largest on the document, stating that it waives rights unconditionally and states that you have been paid, that it is enforceable against you if you sign it even if you have not been paid, and that you should use a conditional release if you have not been paid.
Subsection B and the cost of loose language
B is the reason an email that says "we are all good on this one" does not release anything. A statement purporting to waive or release a claim is enforceable only if it follows the statutory waiver, or if the claimant has actually received payment in full for the claim. When you are collecting waivers as a general contractor, that works for you only when what you collect follows the form. When you are the claimant, the same rule protects you from loose statements you did not mean as releases.
Common mistakes the statute explains
- Signing the unconditional form on handover. Evidence of payment for the conditional form is a paid check or a written acknowledgment; the unconditional form states that payment has already been received.
- Forgetting the through date. The progress forms fix the covered period and leave out later items.
- Treating retention as released. The form says it does not cover retention.
- Using a form from another state. The wording is the Arizona statute's.
Free: lien waiver tracker for multi-tier jobs
One row per party per period, with tier, type, payment cleared date and a check for unconditional waivers with no cleared payment.
Download the lien waiver tracker (xlsx) (no email needed).
Informational only. We summarise A.R.S. 33-1008 as read on 2026-11-23; we do not reproduce the forms and this is not legal advice. Statutes are amended; use the official text and an Arizona construction attorney.
Questions people ask
Does Arizona require the exact statutory form?
Section 33-1008(D) says the waiver and release is unenforceable unless it follows substantially the statutory forms in the circumstances it lists. Substantially is the word used, so small wording differences are not automatically fatal, but a form that leaves out the covered period or the retention carve-out is a different document.
What counts as evidence of payment in Arizona?
Subsection A says evidence of payment may be the claimant's endorsement on a single or joint payee check that has been paid by the bank on which it was drawn, or a written acknowledgment of payment given by the claimant. A conditional release is effective only if there is such evidence.
Can an owner or contractor waive another party's lien in the contract?
Subsection A says an owner or contractor may not, by contract term or otherwise, waive or impair the claims or liens of other persons without their written consent or as the statute allows, and that any contract term to that effect is void.
Are verbal assurances enforceable?
Subsection B says no oral or written statement purporting to waive, release or otherwise affect a claim is enforceable unless it follows the statutory waiver and release or the claimant has actually received payment in full for the claim.
Sources and date checked
Every statute, vendor and price statement on this page was read on the page linked below on the date shown. Where a vendor page did not say something, this page says so instead of guessing. The links go to the original pages, not to summaries.
- Arizona Revised Statutes 33-1008, Waiver of lien (official), checked 2026-11-23